1. Whether Supply of Engineering, Procurement & Construction (EPC) contract for establishment of Integrated Cryogenic Engine & Stage Test facility (ICET) where in both goods and services are supplied can be construed to be a Composite Supply in terms of Section 2(30) of CGST Act, 2017?
2. If Yes, Whether the Principal Supply in such case can be said to be “Establishment of Fluids Servicing System (FSS)” can be taxable at 5% GST vide notification No. 45/2017-Central Tax (Rate) dt 14th November, 2017?
3. If Principal Supply taxable at 5%, whether the entire transaction in the contract is taxed as per the rate applicable to Principal Supply
States/UT
Order No. & Date
TN/47/AAR/2019 dated 16.10.2019
Order date
16-10-19
Upload file
Category
97(2)(a)
Year